Systems Integration & Operations · 10 min read

CRM Integration Handover Checklist: 9 Acceptance Tests

Before signing off a CRM or ERP integration, check recovery tests, reconciliation, credentials, monitoring and operational ownership.

Useful Builds ·

Do not sign off a CRM, ERP or finance integration just because the happy-path demo works. Before accepting handover, require evidence that failed transactions can be found, reconciled and recovered; that your business owns the credentials and operating documentation; and that someone is accountable when the original developer is unavailable. A working connection is not yet an operable business system.

This is a practical acceptance framework for Australian operations managers, IT leads and business owners commissioning an API integration. It is deliberately different from choosing a connector or troubleshooting an outage: it explains what to request before final payment and support handover, with testable evidence rather than a generic promise of reliability.

The nine deliverables to request before sign-off

DeliverableEvidence to inspectAcceptance question
1. System and data mapDiagram, field mapping, authoritative owner for each recordWho may change customer, order and invoice data?
2. Credentials and accessBusiness-controlled service accounts, scoped permissions, secret rotation procedureCan we revoke the vendor without disabling the business?
3. Source and deploymentRepository ownership, environment inventory, reproducible release and rollback instructionsCan a second engineer deploy a tested fix?
4. MonitoringDashboard, alert routing, queue age and failed-write metricsWho receives an actionable alert before a customer complains?
5. Failure recoveryRetry policy, exception queue, replay and duplicate-prevention testWhat happens after a timeout that may have committed?
6. ReconciliationBusiness-level comparison report with missing, duplicate and stale recordsCan finance prove the totals and identities agree?
7. Security and privacyData inventory, retention, access audit and incident response contactsWhat personal information crosses the boundary, and why?
8. Support contractSeverity definitions, coverage hours, named owners and escalation pathWho acts during an outage, including weekends?
9. Change managementRegression test set, dependency list, vendor release watch and exit planWhat happens when an API or field changes?

The evidence should live in systems controlled by the buyer, not solely in a supplier's private ticketing account. A PDF runbook without working access, credentials or a verified recovery drill is insufficient.

Set acceptance tests around business outcomes

Agree the expected result for one normal transaction and at least five adverse cases before development finishes. The table below is an illustrative test plan; adjust thresholds and approvals to the business's risk and transaction volumes.

  1. Normal order: Create a test order in the source. Confirm exactly one destination order, mapped amounts, status and shared correlation ID.
  2. Temporary outage: Make the destination unavailable. Verify a visible pending state, bounded retry and alert to the assigned owner.
  3. Unknown commit: Simulate a response timeout after the destination has accepted a write. Retry must not create a second invoice or order.
  4. Bad data: Send an invalid tax code or missing customer reference. Confirm the record enters a reviewable exception state rather than disappearing.
  5. Credential expiry: Revoke a test token. Verify that the error is observable and the documented rotation process restores access.
  6. Missed events: Pause processing beyond the normal replay period and demonstrate a controlled source-to-destination reconciliation/backfill.

Keep test IDs, screenshots, timestamps, expected/actual results and the responsible approver in the handover pack. An automated test suite is valuable, but finance or operations should also sign off the meaning of the resulting business records.

Example: a Salesforce-to-accounting integration at handover

Hypothetical scenario, not a client engagement: a distributor commissions an integration that creates accounting invoices when Salesforce opportunities become Closed Won. The demonstration shows an invoice arriving within a minute. The supplier says the work is complete.

The business should ask what happens if the accounting API creates an invoice but the confirmation response is lost. The integration needs a stable business request key, a destination lookup or idempotent write contract, and a manual review path for ambiguous outcomes. The finance owner should receive a report matching Salesforce opportunities to destination invoice IDs, totals, currencies and posting status. A successful API response alone is not proof that books reconcile.

For a deeper explanation of unknown commits and safe replay, see our Salesforce integration failure recovery guide. For architecture selection before the project starts, see connectors versus middleware versus custom APIs.

What monitoring and recovery should actually prove

At minimum, the operator needs the oldest pending transaction, recent failed writes, undelivered messages, reconciliation differences and the ability to trace a transaction across systems. Configure an alert owner, not just an email distribution list. Record how incidents are acknowledged, escalated and closed.

A dead-letter queue is a holding area for messages that cannot be delivered successfully; it is not an automatic fix. AWS's EventBridge monitoring guidance recommends monitoring failed deliveries, latency and dead-lettered messages. Its dead-letter queue documentation describes failures that require intervention, including permissions and missing targets. These are AWS-specific examples of general controls; a Salesforce, Azure or other implementation needs its own equivalent.

Retries are not a substitute for idempotency. The AWS Builders' Library explains why the same caller request ID should identify repeated attempts. If the receiving system cannot guarantee safe duplicate handling, define a reconciliation and human-approval step before replaying financial transactions.

Who should own what after the vendor leaves?

ResponsibilityBusiness ownerTechnical owner
Data correctnessFinance / operations approves reconciliationMaintains comparison jobs and evidence
Incident responseSets impact and escalation priorityInvestigates alerts, retries and fixes
Access controlApproves access and vendor offboardingRotates credentials, reviews permissions
ChangesApproves business rule changesTests, deploys and documents releases

Ownership does not require a large internal IT team. A small business can outsource technical support, provided it controls its accounts, source access, monitoring visibility and escalation arrangements. For Salesforce, dedicated integration identities and scoped permission sets are preferable to using an employee's personal login; the exact licensing and authentication design must be checked for the products in use.

Contract language worth agreeing before final payment

Ask suppliers to define a handover milestone based on demonstrated recovery, not only deployment. The milestone might require: buyer-owned repository and credentials; a witnessed adverse-case test; an accepted reconciliation report; a runbook and support roster; a documented rollback; and an agreed period for correcting defects found during acceptance. These are negotiation points, not a universal legal template. Obtain legal review for material contracts.

Separate warranty fixes from ongoing enhancements. A new field or business process may be a change request; a missing retry safeguard that was part of the agreed acceptance criteria is different. Define these boundaries in writing before commissioning work.

When to request an independent integration handover review

Consider an independent review when the original vendor is leaving, your integration relies on one person's knowledge, failures are visible only to the developer, or finance cannot reconcile source and destination transactions. A focused review should produce an inventory of critical flows, a prioritised risk list, access gaps, a recovery test and a practical ownership plan—not a blanket recommendation to rebuild everything.

If you are planning a new connection, compare the available approaches in our build, buy or integrate decision guide. If you are inheriting an existing integration, Useful Builds offers systems integration and API engineering. You can describe the systems and handover problem for a focused discussion of scope.